Fujairah Desalination Plant
- Theme
- EPC
- Client
- ETIHADWE
- Country
- UAE
- Status
- Ongoing
Scope of Work
SWRO desalination plant; design capacity 30 MIGD (136,500 m³/day) during early operation, expandable to 60 MIGD; includes full design, engineering, procurement, construction, commissioning, and completion of potable water production facilities with storage, auxiliaries, and system interfaces.
Seawater intake: Offshore and onshore intake system including marine pipelines (2 × DN2000 offshore; 2 × DN1500 onshore), intake structures, and seawater chlorination facilities.
Brine outfall: Offshore and onshore outfall system including marine pipelines (DN2200) with diffuser arrangement for compliant brine discharge to marine environment.
Product water transfer/pumping: Export system including pumping station (3 pumps, capacity ~1.58 m³/s @ 25 bar), transmission pipelines, and network interface arrangements.
Water treatment: Pre-treatment and SWRO process system including reverse osmosis membrane trains, post-treatment, and potable water storage facilities.
Civil & electrical: Process buildings, plant infrastructure, 33 kV gas insulated switchgear (GIS), chemical dosing systems, control facilities, and associated infrastructure works.
EPC delivery: Full EPC execution including design, procurement, civil, MEP, E&I installation, testing, commissioning, and performance validation.